How Long Does It Take to Fit a Kitchen?

A kitchen takes 2 to 5 days to fit for most fit-only jobs, 4 to 6 days for a supply-and-fit kitchen, and 2 to 3 weeks for a full renovation. A small kitchen of up to 8 units can be fitted in 2 to 3 days, while flat-pack assembly, quartz worktops, plastering and structural work all add time. These are the timings we work to at Kitchen Fitter Glasgow, fitting kitchens across Glasgow and Renfrewshire.

Fitter levelling a run of rigid kitchen base units before the worktop goes on
Illustration

How long does each type of kitchen job take?

The time on site depends mostly on the type of job and the size of the kitchen. This table shows our typical times and what makes each job take longer.

JobTypical time on siteWhat adds time
Fit-only, small kitchen2 to 3 daysFlat-pack assembly, removing the old kitchen
Fit-only, standard kitchen3 to 5 daysFlat-pack assembly, tall housings, uneven walls
Fit-only, large kitchen or island5 to 7 daysIslands needing services run through the floor
Supply and fit4 to 6 daysStrip-out, moving the sink or hob
Full kitchen renovation2 to 3 weeksPlaster drying time, structural work, tiling
Laminate worktop replacement1 dayGas hob disconnection and reconnection
Old kitchen removalHalf a day to 1 dayTiles fixed to the units, a large kitchen

For prices to go with these timings, see our Glasgow kitchen fitting price guide.

What does a three-day kitchen fit look like?

A small kitchen of up to 8 rigid units, with the old kitchen already removed, is often fitted in three days. This is how those days usually run:

DayMorningAfternoon
Day 1Walls and floor checked, levels marked, services locatedBase units set out, levelled and fixed
Day 2Wall units hung; tall housing fittedWorktops cut, joined and scribed; sink and hob cut-outs sealed
Day 3Sink, tap and appliances fitted; any gas or electrical connections by partner tradesDoors, drawers, plinths and end panels fitted; clean and walk-through

A larger kitchen follows the same order, with more time at each stage. Our fit-only kitchen fitting page shows how a standard five-day fit runs.

What makes a kitchen fit take longer?

Seven things add the most time to a kitchen fit. Most of them can be planned for at the survey, so they're in your timeline from the start rather than a surprise on the day.

Flat-pack assembly

Flat-pack kitchens, such as IKEA's, arrive as boxes of panels, and every cabinet has to be built before it can be fitted. Assembly adds 1 to 2 days to a typical kitchen. Rigid units, such as DIY Kitchens and Howdens, arrive ready-built and skip this stage.

Removing the old kitchen

Stripping out an old kitchen, disconnecting the services safely and taking the waste away usually takes half a day to a day. Tiles fixed to the old units or worktops can add time, as can a kitchen built into the walls.

Moving plumbing, gas or electrics

Keeping the sink, hob and sockets where they are is quickest. Moving them means new pipework, a gas connection by a Gas Safe registered engineer or new circuits by a certified electrician, which can add a day or more depending on the distance.

Uneven walls and floors

Older homes, especially Glasgow tenements, often have walls that aren't square and floors that slope. Levelling every unit and scribing worktops to the wall takes longer than fitting into a new-build room, but it's what makes the finished kitchen look right.

Quartz worktops

Quartz is made to measure off site, so it can't be templated until the base units are fitted and level. The worktops are then made and fitted on a second visit, usually one to two weeks later. A temporary worktop can keep the kitchen usable in between.

Plastering and drying time

In a renovation, fresh plaster needs time to dry before it can be tiled or painted. This is the main reason a full renovation takes 2 to 3 weeks rather than one.

Missing or damaged parts

A missing plinth, end panel or hinge pack can hold up the last day of a fit. Checking the delivery against the order the day it arrives is the best way to avoid it.

How long does a tenement kitchen fit take?

A small tenement galley kitchen usually takes 2 to 3 days to fit, and a larger tenement kitchen 3 to 5 days, the same as a house of the same size plus any extra time the building needs. Three tenement features add time:

  • Walls and floors: scribing worktops to uneven walls and levelling each unit on a sloping floor can add part of a day
  • The stair: carrying every unit and worktop up a common stair takes longer on a top floor, and long worktops may need an extra joint planned in
  • Parking and access: controlled parking or a narrow street can slow deliveries and the strip-out, so we plan van access before the start date

A full tenement renovation still takes 2 to 3 weeks. Our tenement kitchen fitting page explains the method in detail.

How long from first call to a finished kitchen?

The time from your first call to a finished kitchen is longer than the time on site, because the kitchen has to be surveyed, quoted, ordered and delivered first. These are the stages:

StageWhat happensHow long
1. SurveyWe measure the room and check walls, floors and servicesArranged at a time that suits you
2. QuoteYou receive a fixed written quoteShortly after the survey
3. Order and deliveryYou or we order the kitchen; delivery is booked before the start dateVaries by supplier, from days to several weeks
4. FittingThe kitchen is fitted2 days to 3 weeks, depending on the job
5. Quartz worktops (if chosen)Templated, made and fittedAdds about 1 to 2 weeks
6. Building warrant (if removing a wall)Engineer's design, application and council reviewAdds several weeks before work starts

If you're removing a load-bearing wall, our guide on when a building warrant is needed explains the extra steps.

How long do kitchen deliveries take?

Kitchen delivery times depend on the supplier and the range, so check the lead time when you order and tell us the date. We then book the fit for just after delivery. These are the patterns to expect:

SupplierHow delivery usually worksWhat to plan for
IKEACollect from IKEA Glasgow at Braehead or book IKEA deliveryFlat-pack boxes need a dry room until assembly
DIY KitchensEach order is booked into a scheduled delivery slotChoose a slot a few days before your fitting date
HowdensOrdered through a trade account and supplied from a depotWe arrange the order and timing for you
Wren, B&Q, Wickes, MagnetDelivered on the retailer's scheduleCheck the range's lead time before you book a start date

Whatever the supplier, a delivery a few days before fitting is ideal. It leaves time to check every box without the kitchen sitting in your hall for weeks.

How can you make a kitchen fit quicker?

You can't rush good fitting, but you can stop time being lost. These steps keep a kitchen fit on schedule:

  • Choose rigid units if you want the shortest fit, as there's nothing to assemble
  • Make your choices before ordering, including appliances, sink, tap and handles, so nothing is changed mid-fit
  • Check the delivery straight away and report missing or damaged items before fitting day
  • Have every appliance on site before the start date, with its installation instructions
  • Clear the kitchen completely the day before we start
  • Book old-kitchen removal as part of the same job, so strip-out and fitting run straight on from each other

How long will you be without a working kitchen?

With a fit-only or supply-and-fit kitchen, you're usually without a working kitchen for about as long as the fit takes, typically 2 to 6 days. The sink is often reconnected before the last day, which makes a big difference. With a full renovation, plan for 2 to 3 weeks and set up a temporary kitchen in another room with a kettle, microwave and fridge. Our kitchen renovation page has a full guide to living without a kitchen.

When can you use your new kitchen?

You can usually use a new kitchen as soon as the fitter hands it over, with a few short waits for finishes that need to set:

  • Sink and tap: ready to use straight away, but avoid soaking the fresh silicone seal for about 24 hours
  • Laminate worktops: usable the same day; keep water off the joints while the sealant cures
  • Solid wood worktops: follow the oil manufacturer's drying time before heavy use, and wipe up water rather than leaving it
  • Quartz worktops: usable once fitted, though the fitter may ask you to go gently on the joints for the first day
  • Gas and electrics: ready once the Gas Safe engineer or electrician has tested and signed off their work

Is it quicker to fit a kitchen yourself?

Rarely. A professional fitter works with the right tools every day and knows the order to do things in, so a kitchen that takes us 3 days can take a first-time DIY fitter several weekends. Worktop joints, scribing and levelling take the longest to learn. If time matters, a professional fit is usually the quickest way to a finished kitchen.

Get a timeline for your kitchen

Tell us about your kitchen, and after a free home survey we'll give you a fixed written quote with the number of days on site.

Kitchen fitting time questions

How many days will the fitter be in my home?

Most fit-only kitchens take 2 to 5 days: 2 to 3 days for a small kitchen of up to 8 units and 3 to 5 days for 9 to 15 units. Supply and fit takes 4 to 6 days on site, and a full renovation with plastering, tiling and flooring takes 2 to 3 weeks. Your written quote states the expected number of days before you book.

Does an IKEA kitchen take longer to fit?

Yes, by 1 to 2 days compared with a ready-built kitchen of the same size, because every flat-pack cabinet has to be assembled before it can be fitted. A small IKEA kitchen of 8 cabinets usually takes 3 to 5 days in total. Our IKEA kitchen fitting page has timings and prices for larger IKEA kitchens, including the cost of assembly.

How long does it take to fit kitchen worktops?

Replacing laminate worktops usually takes one day, including refitting the sink and hob. Solid wood takes one to two days because it's oiled before and after fitting. Quartz needs two visits: templating once the units are fitted, then fitting about one to two weeks later, with a temporary worktop available so the kitchen stays usable in between. Your quote shows each visit.

How long does a full kitchen renovation take?

A full kitchen renovation usually takes 2 to 3 weeks on site. The first week covers the strip-out, any structural work, first-fix plumbing and electrics and plastering, the second covers flooring and fitting the units, and the third covers tiling, second fix and handover. Removing a load-bearing wall adds time beforehand, because the building warrant must be granted before that work starts.

Can you fit a kitchen in a day?

Not a whole kitchen. Even a small kitchen of a few units takes at least two days to fit properly, once levelling, worktop cutting, plumbing, appliances and finishing are included. A single job, such as replacing laminate worktops or fitting a few replacement doors, can often be done in a day. We'll always tell you honestly how many days your kitchen needs.

Why is my kitchen fit taking longer than quoted?

The most common reasons are missing or damaged parts, hidden problems found when the old kitchen came out, such as damp or unsafe wiring, and changes to the plan during the fit. A good fitter tells you straight away, explains why, and agrees any change to the timeline and price with you in writing before carrying on with the work.

How far ahead should I book a kitchen fitter?

Book your fitter before you order the kitchen if you can. That lets the fitter check your plan, and lets you match the delivery date to the fitting date. Good local fitters are often booked weeks ahead, especially before Christmas and after the January sales, so getting a survey early gives you the widest choice of start dates and time to fix any problems with the plan.

Can I live in the house while my kitchen is fitted?

Yes. Almost everyone stays at home during a kitchen fit. Expect noise and dust during strip-out and cutting, and no working sink for part of the fit. Setting up a kettle, microwave and fridge in another room makes the days much easier. During a full renovation, the first week is the dustiest, while the old kitchen comes out and walls are plastered.

How long after the survey can you start?

It depends on the kitchen's delivery date and our diary at the time. After the survey you receive a fixed written quote, and a 25% deposit books your start date. We usually set the start date a few days after your kitchen is due to arrive, so there's time to check every box before fitting begins. Your start date is confirmed in writing.