What Order to Renovate a Kitchen: Step by Step
The right order to renovate a kitchen: strip out, first fix, plastering, flooring, units, worktops, second fix, tiling and decorating. With timings.
A kitchen takes 2 to 5 days to fit for most fit-only jobs, 4 to 6 days for a supply-and-fit kitchen, and 2 to 3 weeks for a full renovation. A small kitchen of up to 8 units can be fitted in 2 to 3 days, while flat-pack assembly, quartz worktops, plastering and structural work all add time. These are the timings we work to at Kitchen Fitter Glasgow, fitting kitchens across Glasgow and Renfrewshire.

The time on site depends mostly on the type of job and the size of the kitchen. This table shows our typical times and what makes each job take longer.
| Job | Typical time on site | What adds time |
|---|---|---|
| Fit-only, small kitchen | 2 to 3 days | Flat-pack assembly, removing the old kitchen |
| Fit-only, standard kitchen | 3 to 5 days | Flat-pack assembly, tall housings, uneven walls |
| Fit-only, large kitchen or island | 5 to 7 days | Islands needing services run through the floor |
| Supply and fit | 4 to 6 days | Strip-out, moving the sink or hob |
| Full kitchen renovation | 2 to 3 weeks | Plaster drying time, structural work, tiling |
| Laminate worktop replacement | 1 day | Gas hob disconnection and reconnection |
| Old kitchen removal | Half a day to 1 day | Tiles fixed to the units, a large kitchen |
For prices to go with these timings, see our Glasgow kitchen fitting price guide.
A small kitchen of up to 8 rigid units, with the old kitchen already removed, is often fitted in three days. This is how those days usually run:
| Day | Morning | Afternoon |
|---|---|---|
| Day 1 | Walls and floor checked, levels marked, services located | Base units set out, levelled and fixed |
| Day 2 | Wall units hung; tall housing fitted | Worktops cut, joined and scribed; sink and hob cut-outs sealed |
| Day 3 | Sink, tap and appliances fitted; any gas or electrical connections by partner trades | Doors, drawers, plinths and end panels fitted; clean and walk-through |
A larger kitchen follows the same order, with more time at each stage. Our fit-only kitchen fitting page shows how a standard five-day fit runs.
Seven things add the most time to a kitchen fit. Most of them can be planned for at the survey, so they're in your timeline from the start rather than a surprise on the day.
Flat-pack kitchens, such as IKEA's, arrive as boxes of panels, and every cabinet has to be built before it can be fitted. Assembly adds 1 to 2 days to a typical kitchen. Rigid units, such as DIY Kitchens and Howdens, arrive ready-built and skip this stage.
Stripping out an old kitchen, disconnecting the services safely and taking the waste away usually takes half a day to a day. Tiles fixed to the old units or worktops can add time, as can a kitchen built into the walls.
Keeping the sink, hob and sockets where they are is quickest. Moving them means new pipework, a gas connection by a Gas Safe registered engineer or new circuits by a certified electrician, which can add a day or more depending on the distance.
Older homes, especially Glasgow tenements, often have walls that aren't square and floors that slope. Levelling every unit and scribing worktops to the wall takes longer than fitting into a new-build room, but it's what makes the finished kitchen look right.
Quartz is made to measure off site, so it can't be templated until the base units are fitted and level. The worktops are then made and fitted on a second visit, usually one to two weeks later. A temporary worktop can keep the kitchen usable in between.
In a renovation, fresh plaster needs time to dry before it can be tiled or painted. This is the main reason a full renovation takes 2 to 3 weeks rather than one.
A missing plinth, end panel or hinge pack can hold up the last day of a fit. Checking the delivery against the order the day it arrives is the best way to avoid it.
A small tenement galley kitchen usually takes 2 to 3 days to fit, and a larger tenement kitchen 3 to 5 days, the same as a house of the same size plus any extra time the building needs. Three tenement features add time:
A full tenement renovation still takes 2 to 3 weeks. Our tenement kitchen fitting page explains the method in detail.
The time from your first call to a finished kitchen is longer than the time on site, because the kitchen has to be surveyed, quoted, ordered and delivered first. These are the stages:
| Stage | What happens | How long |
|---|---|---|
| 1. Survey | We measure the room and check walls, floors and services | Arranged at a time that suits you |
| 2. Quote | You receive a fixed written quote | Shortly after the survey |
| 3. Order and delivery | You or we order the kitchen; delivery is booked before the start date | Varies by supplier, from days to several weeks |
| 4. Fitting | The kitchen is fitted | 2 days to 3 weeks, depending on the job |
| 5. Quartz worktops (if chosen) | Templated, made and fitted | Adds about 1 to 2 weeks |
| 6. Building warrant (if removing a wall) | Engineer's design, application and council review | Adds several weeks before work starts |
If you're removing a load-bearing wall, our guide on when a building warrant is needed explains the extra steps.
Kitchen delivery times depend on the supplier and the range, so check the lead time when you order and tell us the date. We then book the fit for just after delivery. These are the patterns to expect:
| Supplier | How delivery usually works | What to plan for |
|---|---|---|
| IKEA | Collect from IKEA Glasgow at Braehead or book IKEA delivery | Flat-pack boxes need a dry room until assembly |
| DIY Kitchens | Each order is booked into a scheduled delivery slot | Choose a slot a few days before your fitting date |
| Howdens | Ordered through a trade account and supplied from a depot | We arrange the order and timing for you |
| Wren, B&Q, Wickes, Magnet | Delivered on the retailer's schedule | Check the range's lead time before you book a start date |
Whatever the supplier, a delivery a few days before fitting is ideal. It leaves time to check every box without the kitchen sitting in your hall for weeks.
You can't rush good fitting, but you can stop time being lost. These steps keep a kitchen fit on schedule:
With a fit-only or supply-and-fit kitchen, you're usually without a working kitchen for about as long as the fit takes, typically 2 to 6 days. The sink is often reconnected before the last day, which makes a big difference. With a full renovation, plan for 2 to 3 weeks and set up a temporary kitchen in another room with a kettle, microwave and fridge. Our kitchen renovation page has a full guide to living without a kitchen.
You can usually use a new kitchen as soon as the fitter hands it over, with a few short waits for finishes that need to set:
Rarely. A professional fitter works with the right tools every day and knows the order to do things in, so a kitchen that takes us 3 days can take a first-time DIY fitter several weekends. Worktop joints, scribing and levelling take the longest to learn. If time matters, a professional fit is usually the quickest way to a finished kitchen.
Tell us about your kitchen, and after a free home survey we'll give you a fixed written quote with the number of days on site.
Most fit-only kitchens take 2 to 5 days: 2 to 3 days for a small kitchen of up to 8 units and 3 to 5 days for 9 to 15 units. Supply and fit takes 4 to 6 days on site, and a full renovation with plastering, tiling and flooring takes 2 to 3 weeks. Your written quote states the expected number of days before you book.
Yes, by 1 to 2 days compared with a ready-built kitchen of the same size, because every flat-pack cabinet has to be assembled before it can be fitted. A small IKEA kitchen of 8 cabinets usually takes 3 to 5 days in total. Our IKEA kitchen fitting page has timings and prices for larger IKEA kitchens, including the cost of assembly.
Replacing laminate worktops usually takes one day, including refitting the sink and hob. Solid wood takes one to two days because it's oiled before and after fitting. Quartz needs two visits: templating once the units are fitted, then fitting about one to two weeks later, with a temporary worktop available so the kitchen stays usable in between. Your quote shows each visit.
A full kitchen renovation usually takes 2 to 3 weeks on site. The first week covers the strip-out, any structural work, first-fix plumbing and electrics and plastering, the second covers flooring and fitting the units, and the third covers tiling, second fix and handover. Removing a load-bearing wall adds time beforehand, because the building warrant must be granted before that work starts.
Not a whole kitchen. Even a small kitchen of a few units takes at least two days to fit properly, once levelling, worktop cutting, plumbing, appliances and finishing are included. A single job, such as replacing laminate worktops or fitting a few replacement doors, can often be done in a day. We'll always tell you honestly how many days your kitchen needs.
The most common reasons are missing or damaged parts, hidden problems found when the old kitchen came out, such as damp or unsafe wiring, and changes to the plan during the fit. A good fitter tells you straight away, explains why, and agrees any change to the timeline and price with you in writing before carrying on with the work.
Book your fitter before you order the kitchen if you can. That lets the fitter check your plan, and lets you match the delivery date to the fitting date. Good local fitters are often booked weeks ahead, especially before Christmas and after the January sales, so getting a survey early gives you the widest choice of start dates and time to fix any problems with the plan.
Yes. Almost everyone stays at home during a kitchen fit. Expect noise and dust during strip-out and cutting, and no working sink for part of the fit. Setting up a kettle, microwave and fridge in another room makes the days much easier. During a full renovation, the first week is the dustiest, while the old kitchen comes out and walls are plastered.
It depends on the kitchen's delivery date and our diary at the time. After the survey you receive a fixed written quote, and a 25% deposit books your start date. We usually set the start date a few days after your kitchen is due to arrive, so there's time to check every box before fitting begins. Your start date is confirmed in writing.
Timings are our own, based on 15 years of fitting kitchens across Glasgow and Renfrewshire, and are confirmed for each job in a written quote. Supplier information was checked on 10 and 11 November 2026.